Digging to continue today.
8:33am- pit is dug out and the east bank will be tapered back today to help with cave offs.
11:43am- pit now has ramp cut in for skidsteer access for applying gravel to level up footings and pad.
3:20pm- crew has marked out some points inside pit and have also unloaded semi load of rebar.