Lakeway Village WWTF-Lift Stations


Crew will finish build the road on Pike St lift station and then begin moving equipment to other site nearest Bluegill St. 
9:00am- crew has moved Excavator to other site now and will begin clearing and grubbing site. 

Fencing for both sites to begin next Monday the 19th. 

12:00pm-Rock is showing as septic tank is removed. Contractor has requested moving entire station site to the right 5 feet to clear rock ledge. Contact has been made with Engineer on this issue. 

Oversized anti- Float flange doesn’t help matters either...

5:30pm- lift station is now set in place as main line will now be getting connected. Pipe has broken at a eye, so that will now be changed out. 





6:00pm- McClanahan crew running to find parts to get sewer tied into basin yet tonight. Everything should be up and running here shortly for tonight. 

Electricians still onsite doing their electrical. 