Tuesday, August 15, 2017

Lakeway Village WWTF


Influent sampling manhole is set in place. 

Risers on tanks are getting formed up today. 

11:30am- manhole #2 is set and piping ran and connected to septic tank. 

Manhole #3 now has lines connected and tied to recirculation tank and to MBBR. 

4:10pm- sampling manhole now has concrete poured in it and around it to seal piping. 

Continuation of risers on tanks as rebar is placed before put side forms are set in place. 