RipRap will begin being placed today.
Pipe work to continue.
11:56am- RipRap is now laid on n place along North East end of project.
4" pipe has also been disconnected from 8" pipe due to it being in the wrong location and pipe.
4:00pm- 8" line from filters is now tied back into recirculation tank. Line and valve from MBBR is now being dug for running 6" return back to septic tank 1.
4:30pm- end of day.