Monday, August 21, 2017

Lakeway Village WWTF


RipRap will begin being placed today. 

Pipe work to continue. 

11:56am- RipRap is now laid on n place along North East end of project. 

4" pipe has also been disconnected from 8" pipe due to it being in the wrong location and pipe. 

4:00pm- 8" line from filters is now tied back into recirculation tank. Line and valve from MBBR is now being dug for running 6" return back to septic tank 1. 



4:30pm- end of day. 