Monday, September 11, 2017

Lakeway Village WWTF


Crew to pour UV structure today. 

11:20am- UV structure is now poured. Crew continues to work inside tanks today to get piping in place and grouted into walls at pass throughs. 



4:15pm- pipe and Tees are now installed through walls in the septic tanks. 

Crew continues with pump piping installation inside of recirculation tanks at this time. 

5:00pm- end of the day. 