Crew will be working on getting piping through the walls today at recirculation tanks.
Alignment to pump stands is underway.
11:00am- form work and ties going in.
4:50pm- horizontal rebar is now in place and tied. Wall Tye's are also in place. Outside of wall forms to go on tomorrow. No piping was placed through recirculation walls today due to missing fittings.