Crew grouting UV structure this Am preparing it for backfill.
Last valve and connection going in on Recirculation lines on tank #1.
10:20am- last valve now in place and grouting taking place now.
2:30pm- gravel backfill going in now at Recirculation Tanks' piping connections.
More grading to be done around the site for building pad and such yet today.