Thursday, September 7, 2017

Lakeway Village WWTF


Outfall connection to the MBBR with 8" pipe is getting accomplished this AM. 



11:25am- reducer fitting to take piping from 6" to 4" still have not arrived onsite yet today. Therefore,
 outside forms are being installed on the UV structure tat this time. 

4:35pm- forms are now completed. Champher strips are on also now. Reducers arrived today and are in the vault bolted up. 

5:00pm- end of the day. 