5:40am- crew awaiting concrete to begin pour for filter floor today. Testing of concrete will occur onsite as well today.
6:12pm- floor is done.
Cylinders were pulled every 50 yards in sets of three. Total of 15.
And more rebar appears to be standing at septic and recirculating tanks.