Walls will be poured in short sections due to the amount of rebar in walls and getting it vibrated in place. Water stop and key ways are being used at the end of the forms. Pour today at 1pm.
1:38pm- pumping of concrete is underway and testing is completed. Air; 5.25%, Slump; 6", Temp; 84*F. 3 cylinders have also been made.
3:25pm- pour on this section of wall is now complete.
Next pour is tentatively scheduled for next Monday at 3pm.