Filter pad gravel will continue to be placed as rebar will begin to be tied for floor.
7:30am- forms are being placed along with rebar today for filter floor.
11:30am- crew hard at it tying rebar.
4:20pm- 1/2 of the floor rebar now tied for the filter floor. Gravel is also placed and floor extended on out to about 3/4. Rest of gravel will be placed tomorrow.
4:30pm- crew calls it a day.