Crew to begin forming next section of walls to septic tank #2.
8:00am- crew working to remove forms from wall poured yesterday.
11:20am- panel forms going in on septic tank 2 walls.
4:00pm- forms for pour at 2:30pm tomorrow are now mostly up on septic tank 2. The headers at the end walls will be finished out in the morning.
4:30pm- end of the day for the crew.