Forms going up this AM so that a pour can be done late this afternoon. 
8:00am- boards at key way on end of wall are being removed before forms go up. 
 
11:30am- inner forms are up as a pour is scheduled for 3:30pm today. 
 
3:50pm- Update. Pour is delayed as pump truck is tied up on another job. Concrete to now be onsite at 5:00pm yet today. 
 
5:05pm- pump truck has arrived. 
 
6:14pm- awaiting next truck load of concrete. Air: 6.5%, slump: 7", Temp: 80*F.  3 cylinders made. 
 
6:48pm- pour now completed. 29yds. 
 