Forms going up this AM so that a pour can be done late this afternoon.
8:00am- boards at key way on end of wall are being removed before forms go up.
11:30am- inner forms are up as a pour is scheduled for 3:30pm today.
3:50pm- Update. Pour is delayed as pump truck is tied up on another job. Concrete to now be onsite at 5:00pm yet today.
5:05pm- pump truck has arrived.
6:14pm- awaiting next truck load of concrete. Air: 6.5%, slump: 7", Temp: 80*F. 3 cylinders made.
6:48pm- pour now completed. 29yds.