Thursday, November 16, 2017

Lakeway Village WWTF


Pump lift bales have been installed. 

Crew building UV cleaning stand. Light pole stands to be dug out today and poured with concrete. 

12:20pm- lamp post holes are dug and rebar has been inserted into sonotubes. Bolts are also ready for install. 





Electricians are also here with SCADA tech for installation of such at this time. 

5:00pm- concrete has been poured in pole pedestals and mounting bolts set in place. 

Generator gets fuel today to 1/2 tank by the gauge. 

Site work was also done with grading. 