Monday, November 6, 2017

Lakeway Village WWTF


7:00am- more gravel was hauled in over the weekend. 

Belt truck is onsite. 

Filters getting final leaves removed. 

8:14am- gravel is going in at this time and will continue until completed. 







8:36am- base coarse almost completed on filter 2. 

8:45am- filter 2 base layer completed. 

8:48am- filter 1 starts. 

9:10am- 1/3 done. 

10:00am- second layer of gravel going in. Approximately 5/8” in size. 

11:07am- second layer completely finished, both filters. Now pouring rain. 

11:23am-  1/4” gravel going in now...still pouring rain. 

1:10pm- 1/4” gravel progressing. Still on filter 2. 

2:50pm- filter 2 is now about finished out to top pipe grade. 

4:30pm- distribution header going in on filter 2 now. 

 1/4” gravel going in on filter 1 also at this time. 

5:15pm- crew prepares to call it a day. 