Lakeway Village WWTF


Gravel base going down along with weed control. Start up on pumps to occur today. No set time as of this posting. 





8:00am- JCI to be onsite between 9-9:30am to do start up on pumps. 
9:30am- pumps on recirculation tank are pulled so that oil can be checked in them. Generator start up is also onsite for start up. 



12:00pm- recirculation tank 2, pump 2 is now running with an arch height of roughly 42”. 

12:30pm- recirculation tank 2, pump 1 is runnng now with an arch height of  32”. 

1:05pm- recirculation tank 1, pump 1 now running with an arch height of 40”. 

1:30pm- recirculation tank 1, pump2 now running with an arch height of roughly 37”. 

4:35pm- UV, MBBR & Blowers to be started up tomorrow morning around 8:30am. 