A pipe threader will be put together today so air lines can be plumbed in. Building to arrive onsite today and gravel is to begin getting delivered for filters.
9:30am- generator now onsite.
11:05am- Air lines are now underway. Piping is getting cut and threaded.
12:33pm- building arrives onsite.
1:53pm- now set in place and door is getting hanged.