Lakeway Village WWTF


Possible pad pour today. Gravel to be delivered though and will need to be pushed up as it is hauled in. 

12:00pm- forms are now finished for gen pad and in front of doorway at building. 



Gravel is pushed up as it gets hauled in today. 

5:00pm- small gravel is now onsite and will be getting pushed up as hauling continues. Rebar has been placed in pads as well today. 