Monday, October 30, 2017

Lakeway Village WWTF


Gutters are now installed on control bldg. Last Friday ended up being a work day here due to the rain day last Monday. 



Almost half of the top layer of gravel is now onsite. 

Flow is measured this AM in septic tank #1- 7’-2”. Flow will spill over at 7’-6”. 
12:00pm- miscellaneous items being taken care of today. 
Painting of piping. 

Chipping of concrete around risers. 

Septic tank #1 level about 2” from spilling into septicvtank 2 also at this time. 

4:30pm- septic tank#1 is right at spilling over into septic tank #2. 

Electricians are getting things wired in. 

More rock gets delivered today. 