Air line is now installed to MBBR.
Bottom and middle layers of gravel delivered. 1500 ton to begin getting delivered today for top layer.
11:14am- control panel now sits inside of building.
...and layout for generator pad begins.
4:00pm- sealant has been applied around building at this time.
...and from g out of the generator pad continues. Gravel base has been laid and compacted.