Sewer line to be tied in today and septic tank by passed.
8:17am- a tee connection has been found and will now be chased back to find turn in pipe.
9:15am- generator now set in place.
10:18am- appropriate angle to manhole is now located for the 4” tie in from subdivision.
1:55pm- 4” line now connected to Manhole and gravel rd in place.
Subdivisions step system effluents are now entering the new plant at septic tank #1.
3:30pm- Old septic tank has been pumped and collapse
onsite. Old line is plugged and backfill is done followed by compaction.