Tuesday, October 17, 2017

Lakeway Village WWTF


More pea gravel to be delivered today. Crew to mount UV light brackets today. 

11:00am- mounting of UV racks now taking place. 

...and gravel continues to be pushed up. 

5:00pm- UV bulb racks are now mounted in place. 

...and concrete pads were poured today also;



along with the stem wall on MBBR. 