Monday, July 10, 2017

Lakeway Village WWTF

Crew stripping forms from recirculation tank and will begin forming on sand filter walls today. 


11:30am- crew today pour 1st section of wall on filters at 2:30pm today. 

3:05pm- awaiting 2nd truck to arrive onsite. Concrete tested today with the following results;
Air: 5%, Slump 6", Temp: 83*F.  3 cylinders made. 