Lakeway Village WWTF


Crew tying rebar today. Pour scheduled for the 3rd of August. 

9:53am- rebar still being laid and tied in place. Layout for additional "cleanouts" will persue. 

12:5pm- bottom layer of rebar is now down. Spacers are set in place for top layer to bet installed this afternoon. Additional "cleanouts" will now be placed on Monday. Pour has also been rescheduled for August 1st. 

I will now be offsite. 