Crew breaking down forms and moving them to another section of wall for a pour today around 2:30pm.
12:00pm- forms are now in place for pour today.
2:25pm- plugging & grouting of tie holes on basins' walls are underway today.
This plug is inserted into wall and tightened , then grouting follows.
3:25pm- pour is now complete for today. Testing done.
Air: 7%, Slump 7", Temp 84*F. 3 cylinders made.