Crew putting final touches on tying of the rebar this AM. Additional "cleanout" points have been marked out as well.
11:00am- rebar is now tied and "cleanouts" have been inserted into the rebar. Vents stacks get a coat of galvanized paint.
4:20pm- top is ready to pour. Pour is scheduled for 5:30am in the morning. Crew is offsite at this time.