Forms are pulled and are getting moved to another section of wall for the filters today. Pour to be at 2:30pm.
3:20pm- pour is completed for today. Another 14 yards went into the walls on the gravel filter bed. Testing was again done: Air 6%, Slump 6.5", Temp 85*F.
3 cylinders were made.
No comments:
Post a Comment