Wednesday, July 19, 2017

Lakeway Village WWTF


Crew packaging up forms to be hauled offsite today as dirt work continues. 

MBBR to arrive today. It will be a precast unit. 

10:30am- forms are now removed from filter and clean up begins for internal piping layout and the 12" 80/20split wall. 

The other side is already formed and laid out. 

5:22pm- MBBR structure arrived today and the crew just finished pouring a bottom in it. I had them create the anti-float flange around it although it wasn't shown on submittal. 

Crew calls it a day. 