Monday, July 17, 2017

Lakeway Village WWTF


Crew moving forms to another section of wall today. A Pour is scheduled for 2:30pm- 

10:10am- backfill and compaction begins today around septic and recirculation tanks. 



1:30pm- forms are in place for pour today as backfill continues. 

3:25pm- pour is all but done today. Testing of concrete was performed. Air:7%, Slump 7.5", Temp: 86*F.  3 cylinders were made. 